DOSH是马来西亚Department of Occupational Safety and Health (DOSH),
Approval and Authorisation
The approval and authorisation procedures issued by the Department were for the design of steam boilers, unfired pressure vessels, and hoisting machinery, whereas the authorisation to install was issued for general machinery.
The guides and procedures for approval done by DOSH are as below:
1. PERSONAL PROTECTIVE EQUIPMENT (PPE)
2. AUDIOMETRY TEST CENTRE (PUA)
3. LIFTS, ESCALATORS & DUMBWAITERS
4. SAND BLASTING
5. HOISTING MACHINE DESIGN
6. PIPELINE DESIGN
7. DESIGN OF UNFIRED PRESSURE VESSELS (UPV)
8. DESIGN OF STEAM BOILERS
9. BOILER & PRESSURE VESSEL HYDROSTATIC TEST
网址:http://www.dosh.gov.my/index.php?option=com_content&view=article&id=531&Itemid=360&lang=en |
|
|