发表于 2014-3-10 14:50:06
|
显示全部楼层
RT 1 - The complete vessel satisfies the full radiography requirements of UW-11(a) and the spot radiography provisions of UW-11(a)(5)(b) have not been applied.
RT 2 - The complete vessel satisfies the full radiography requirements of UW-11(a)(5) and the spot radiography provisions of UW-11(a)(5)(b) have been applied.
RT 3 - The complete vessel satisfies the spot radiography requirements of UW-11(b).
RT 4 - Only part of the vessel has met the other category requirements, or none of the other requirements are applied.
国标里的全拍片就是asme里的RT1局部拍片就是RT3。ASME UW-11(a)(5)(b)允许规定的焊缝局部拍片而焊接接头系数仍然为1,就是RT2。 |
|
|